How do I know I am not overpaying for materials?
The invoice is in your name, the payment leaves your account and the cost sheet stays open. Here are the five safeguards, how to check for yourself and the ways of overpaying that never show up in the price.


On a JP cost-plus build, the invoice is issued to your tax ID, the payment leaves your account and the sheet shows every purchase with a receipt. You see the price the supplier charged, not a price passed on with a margin. And you can check any item at any time by calling the supplier.
This is the fairest question there is on a cost-plus build, because the builder buys and you pay. This page shows the safeguards that answer it, how you can check for yourself and why price is not the only way to overpay.
The five safeguards
- The invoice. Every purchase is in your name, not JP's. The price on it is what the supplier charged.
- The payment. The money goes from your account straight to the supplier. It never passes through the builder's accounts.
- The monthly statement. The sheet lists every item bought, the quantity, the supplier and the value, with the receipt attached. Nothing enters the account without a document.
- The detailed budget. Made before work starts, it says how much of each material the build needs and at what price. Every real purchase can be compared with the forecast.
- Tracking. The site diary, measurements and indicators are in Vobi, and the 24-hour cameras show whether the material bought arrived and was used.
How to check for yourself
You do not need to be an engineer to check. Three simple tests already tell you a lot:
- The phone test. Pick an item from the sheet, call the supplier and ask the price. That is why the invoice is in your name.
- The quote test. Ask for the same item at two other shops. Site prices vary with volume and delivery time, but the difference needs an explanation.
- The quantity test. Compare what was bought with what the detailed budget expected for that stage.
The table below is an example of how to read that quantity comparison. The numbers are illustrative, to show the reasoning:
| Item, example | Forecast | Bought | Difference |
|---|---|---|---|
| Cement, 50 kg bag | 420 bags | 435 bags | +3.6% |
| CA-50 rebar, 10 mm | 1,850 kg | 1,850 kg | 0% |
| Living room porcelain tile | 96 m² | 118 m² | +22.9% |
A small difference on cement is normal site loss. A big difference on the tile calls for a question: did the layout change, did pieces break, or is there material left over? The answer may be a good one, but it has to exist.
Price is not the only way to overpay
Many people check the unit price and forget the rest. In practice a build gets expensive in other ways:
- Waste. Material lost to poor cutting plans or poor storage comes out of your pocket all the same.
- Last-minute buying. Material bought in a rush, because nobody planned ahead, almost always costs more and ships worse.
- Rework. The wrong material, or material laid too early, gets paid for twice.
- Material that disappears. Material bought and never used does not show in the price, only in the total. That is what the cameras and the measurement are for.
What about a fixed price?
On a fixed price the question changes shape. You do not see the price of any material, because it sits inside a single number. The way to check becomes different: compare proposals from different builders against the same specification, with the brand, model and quantity of every finish, and check at handover that what was installed is what was written.
What to do if something does not add up
Ask. On a cost-plus build every line of the sheet needs an answer: the invoice, the reason for the difference and where the material went. A builder that works with open books should welcome that question, because it is what shows the controls work.